2013 |
Third Quarter |
Notice of Preparation for Draft Environmental Report (DEIR) |
2014 |
First Quarter |
Draft EIR Released |
Second Quarter |
Final EIR Released |
Third Quarter |
Certification of EIR / Project Approval |
Fourth Quarter |
BOAC Approval of Contract Award |
2015 |
Second Quarter |
NTP for Phase 1: Design |
Fourth Quarter |
Basis of Design Developed |
2016 |
Third Quarter |
60% Design Development / Early Site and Civil Work Authorized |
Fourth Quarter |
Project GMP Approved / NTP for Phase 2 |
2017 |
Third Quarter |
100% Design Development |
2018 |
Second/Third Quarter |
Taxiway T Reopens / Taxiway S Closed |
2019 |
Fourth Quarter |
Taxiway S Reopening |
2020 |
Second Quarter |
Project Substantial Completion |