LANE RESTRICTIONS: SB Sepulveda Boulevard between 98th Street & Century Boulevard
LANE RESTRICTIONS:
SB Sepulveda Boulevard between 98th Street & Century Boulevard
Wednesday, Aug. 20 through Tuesday, Sept. 23, 2025
Work Hours: Nightly from 10 P.M. to 5 A.M. | Lanes Open During Day

Aug. 20, 2025 — To facilitate foundation work for the Airfield and Terminal Modernization Project (ATMP), underground pipelines must be relocated along Sepulveda Boulevard (Phase 1) and continue later along Century Boulevard (Phase 2).
Phase 1 Schedule:
Wednesday, August 20 through Tuesday, September 23.
Work Hours:
Nightly, 10 p.m. to 5 a.m.
All lanes reopened daily outside of work hours.
Traffic Impacts (Sepulveda Boulevard):
Lane Closures: Up to three southbound lanes between 98th Street and Century Boulevard, including right turn to “Little Century” at Park One
At least one southbound lane will remain open at all times; northbound lanes are not impacted.
Flaggers and signage will be in place to facilitate all movements. Please watch for posted signage, use caution when traveling near construction areas, and plan ahead for potential delays.
This Construction Impacts Notice will be followed by a subsequent notice detailing continuing work as part of this project along Century Boulevard.