LINXS Construction Advisory


LANE RESTRICTIONS ON WESTCHESTER PARKWAY AND PERSHING DRIVE FOR UTILITY WORK

To facilitate LADWP excavation and installation of new conduit duct banks for the RS-X Project, portions of Westchester Parkway and Pershing Drive will be restricted Monday, March 14 through Saturday, April 2, Monday through Friday nights from 9 p.m. to 6 a.m. and Saturdays during the day from 7 a.m. to 5 p.m. No work will be performed on Sundays.

Underground work will take place along Westchester Parkway and the west side of Pershing Drive, near Westchester Parkway. This area of Pershing Drive is not in the public right-of-way. On Westchester Parkway, one eastbound lane will be closed with one lane open at all times; westbound lanes will not be affected.

Traffic will be maintained and flaggers will be in place.

 

Dates/Times:

Monday, March 14 through Saturday, April 2
Monday through Friday: 9 p.m. to 6 a.m.
Saturdays: 7 a.m. to 5 p.m.

 

*Dates and times subject to change.

 

 

For additional information about the Landside Access Modernization Program, visit FlyLAX.com/ConnectingLAX.

Footer

Back To Top