Summer 2010
To Summer 2012
|
Terminal 6 |
Terminal 6 is undergoing a complete
Remodeling of its lobbies, baggage claim and security screening facilities |
Upon arrival at Terminal 6, passengers will detour through a re-opened lower level tunnel for easier access to baggage claim, which significantly reduces congestion. The traveling public may also notice barricades, detours, and construction related noise. Operations will continue as normal during renovations.
|
February 2011
To August 2014
|
Central Utility Plant (CUP) adjacent to Theme Building |
The CUP will be completely replaced with a new, modern, state-of-the-art facility to meet the demands of the airport’s modernization |
One north lane of Center Way adjacent to the CUP and Theme Building will be closed during the phased construction including one exit from Parking Structure 3. Other areas of the Central Terminal Area may be slightly impacted as construction phases progress. |